Dr. Santos
LRT-1 station
Dr. Santos station, also called as Sucat station is an under-construction Manila Light Rail Transit (LRT) station situated on Line 1. It is part of the Line 1 South Extension Project. The station would be located in between Dr. Santos Avenue, C-5 Southlink Expressway and C-5 Extension in Parañaque, a few hundred meters behind SM City Sucat.
Dr. Santos | |||||||
---|---|---|---|---|---|---|---|
Construction of Dr. Santos station in April 2023
|
|||||||
General information | |||||||
Location | San Dionisio, Parañaque, Metro Manila, Philippines | ||||||
Owned by | Department of Transportation Light Rail Transit Authority |
||||||
Operated by | Light Rail Manila Corporation | ||||||
Line(s) | Line 1 | ||||||
Platforms | 2 (2 side) | ||||||
Tracks | 2 | ||||||
Construction | |||||||
Structure type | Elevated | ||||||
Other information | |||||||
Status | Under construction | ||||||
Services | |||||||
|
Dr. Santos station was first planned as part of the Line 1 South Extension, which calls for a mostly elevated extension of approximately 11.7 kilometers. The extension will have 8 passenger stations with an option for 2 future stations (Manuyo Uno and Talaba). The project was first approved on August 25, 2000 and the implementing agreement for the project was approved on January 22, 2002. However, construction for the extension was repeatedly delayed until the project was shelved years later.
The plans for the southern extension project were restarted as early as 2012 during the Aquino administration and was expected to begin construction in 2014, but was delayed due to right of way issues. The issues were resolved in 2016 and the project broke ground on May 4, 2017. Meanwhile, construction works on the south extension began on May 7, 2019 after the right-of-way acquisitions were cleared.
As of July 27, 2023, the project is 88% complete; the station itself is 71.1% complete. Phase 1 of the extension (from Redemptorist station to Dr. Santos station) is slated to be operational by the 4th quarter of 2024. with full operations by second quarter of 2027.
Existing stations | |
---|---|
Baclaran
EDSA Libertad Gil Puyat Vito Cruz Quirino Pedro Gil United Nations Central Carriedo |
Doroteo Jose
Bambang Tayuman Blumentritt Abad Santos R. Papa 5th Avenue Monumento Balintawak Fernando Poe Jr. |
Under construction | |
Redemptorist
MIA Asia World Ninoy Aquino |
Dr. Santos
Las Piñas Zapote Niog |
North Triangle |